Roof on new 40 bed Kemare Hospital nears completion

The roofing contractor is now completing the necessary fixings for the steel cladding to the roof.  The total time frame for this phase of the building project was less than 2 months. This  follows the finalising of the block work by Kevin McAllen Building Service (k.mcallen@live.ie) before the start of the summer.  With the cladding now almost finished, the electrical, plumbing and plastering of both the internal and external walls is due to begin in the coming weeks.

 

 